February 2008
Awarding the contract of north-south Tunnel of Tehran metro Line 7, with 14 km length, to Fater Corporation and its foreign counterpart based on Design-Build
|
|
|
 |
March 2008
Awarding the contract of east-west Tunnel of Tehran metro Line 7, with 13 km length, to Hara Corporation based on Design-Build
|
|
|
 |
April 2008
Signing a domestic finance contract of Tehran metro Line 7, among Tehran Municipality, Tehran Urban & Suburban Railway Company (Metro) and Credit & Finance Corporations for a sum of 5000 billions Rials (Iranian Currency)
|
|
|
 |
May 2008
Signing a Memorandum of Understanding (M. O. U.) between Sepasad Engineering Company & a Chinese Company on the base of a Consortium to finance and execute Narmab dam & irrigation system for the employer; Water Company of Golestan Province.
|
|
|
 |
May 2008
Awarding the execution of the station of San'at Square related to Tehran metro Line 7 to the Sepasad' department of the water tightening & deep foundation
|
|
|
 |
May 2008
BC-50 drill rig is released from Bandar Abbas customs and arrived to the Karkheh job site.
|
|
|
 |
June 2008
Sepasad participation in the second national conference & technical fair of hydro power plant
Achieving fifth grade on representing the articles
Achieving third grade on best gallery on the fair
|
|